Internacional announces the long-awaited return of Beira-Rio

Internacional announces the long-awaited return of Beira-Rio


Electricity has already returned to 75% of the stadium

Still with damage caused by the rains, Beira-Rio is expected to return to normal activity in July. The situation of the stadium was updated by Internacional this Thursday (06) and left fans thrilled with the information. Watch!




Updates:

Beira-Rio Stadium:

  • The light has already returned to 75% of the stadium. This Thursday, tests were carried out to recover the missing 25%.
  • The water has partially returned to the complex. Tests for full recovery are still underway.
  • Work began this week on replacing the synthetic turf in the changing rooms and in the pitch access tunnel.
  • The interior furnishings of the Inter sectors on the first floor were damaged. Process of purchasing new furniture in progress.
  • Lawn: winter grass once sown is completed. 14 days left to germinate.
  • Cleaning: Cleaning of the shops and circulation areas on Level 1 began this Thursday. Cleaning of the entire stadium will be completed by the end of next week.
  • The reopening of the complex is scheduled for July.

Little Giant:

  • Cleaning completed.

CT Giant Park:

  • Cleanup completed with the removal of over 50 tons of waste.
  • The rebuilding process began this week.
  • 90 day deadline for completion.